Before reading this article, ensure you have read Measurement - Parts & Labour and Using Formula within Groundplan articles to aid in understanding the following Formula examples.
📝 The Formula values provided in this article are for example purposes only.
Term | Explained |
---|---|
count |
total counts |
len |
total metres measured |
count or len / x |
total count/length divided by an amount |
count or len * x |
total count/length multiplied by an amount |
ceil(x) |
rounding up a decimal value to the next whole number |
Downpipe
Example Parts for a downpipe Count Measurement:
Part | Explanation | Formula | UMO |
---|---|---|---|
100mm DVW pipe (6m) | How many 6m lengths are required to complete downpipes when 3 metres 1/2 length (3m) is needed for each downpipe |
count*0.5 |
lengths |
100mm PVC 90° bend | How many 90° bends are required when 3 are needed for each downpipe |
count*3 |
each |
100mm saddle clip | How many saddle clips are required when 3 are needed for each downpipe |
count*3 |
each |
100mm classic expansion outlet | How many expansion outles are required for each downpipe |
count |
each |
Downpipe nozzle | How many nozzles are required for each downpipe |
count |
each |
(optional) 100mm junction (for 80%) | How many junctions required for 80% of the downpipes needed |
ceil(count*0.80) |
each |
100mm DWV Sewer (av. 1.5m depth)
Example Parts for a 100mm DWV average 1.5m depth Length Measurement:
Part | Explanation | Formula | UMO |
---|---|---|---|
100mm DWV | How many 6m lengths required for the total length measured |
ceil(len/6) |
lengths |
Trench work (1.5m average depth) | How many m3 for the total length measured multiplied by the 600mm wide by 1.5m deep |
len*0.6*1.5 |
m3 |
Crushed rock (400mm average depth) | How many m3 for the total length measured multiplied by the 600mm wide by 400mm deep |
len*0.6*0.4 |
m3 |
Sewer Bend
Example Parts for a sewer bend Count Measurement:
Part | Explanation | Formula | UMO |
---|---|---|---|
100mm 45° bend | Require 2x 45° bends for each 90° count |
count*2 |
each |
100mm DWV | Allowing an additional 600mm of 100mm DWV for each upwards pipe (Grouping with Sewer Measurement) divided by 6m lengths required for the total length measured |
ceil(len*0.6/6) |
lengths |
For Formula assistance, please reach out to Support. Go to: Help > Send us a Message.
Download a PDF copy of Using Formulas within Groundplan here.
Organise your session today! Click Help > Send us a Message and ask to book in for free training.
Trainers can assist with:
- Workflow solutions
- Time-saving tips
- Making sure you're getting the most out of your subscription
If you've accessed your free training and need further Support, reach out to book a 1 or 2 hour paid session.